NPC Construction Update - 5/10/12

NPC Progress: Weeks of April 26 - May 10, 2012

The Geothermal field is completed under the play field and currently undergoing pressure testing. The placing of Hollow-core is ongoing, with a portion of the second floor being placed on May 10. As the masonry work continues, it is starting to look more like a school all the time. The construction is proceeding on schedule and the weather has not hampered progress.